Work Schedule

  • Work is expected to start on April 1st.
  • The work is expected to last 12 – 14 weeks, finishing in July
  • During the works we aim to have 18+ (4-6) holes open every day.
  • As soon as the work is finished on a hole it will become playable, but with the newly turfed areas roped off.
  • We expect to be able to remove the ropes quickly as the turf should root quickly at this time of year.
  • However we will have to see what the weather brings!