The majority of the works for shaping took place on C1 this week. The run off to the left of the green where the original LHS greenside bunker used to be was shaped out. The new bunkers were created and the edges marked out. Capillary Concrete was installed on all bunkers on C1. Durabunker was installed and all top soil was shaped at final grade.
The plan for the week ahead is to install Capillary Concrete in the remaining 7 bunkers on C-Loop, continue to install Durabunker and start installing sand on the completed bunkers as well as continuing with top soil.