The main focus of works during week 6 were the construction of the new turf nursery location to the right hand side of C9 green, this will be a fantastic addition as it will act as a spare green, sown with the same grasses as our existing greens, this will allow us to repair any imperfections in our greens. (See timelapse: Turf Nursery Construction)
Week 7 has begun fantastically well. David Nelson (Greenmakers by Nelson & Vecchio), our main contractor, and his team have finally managed to get into Denmark. Unfortunately due to the restrictions of travel from Covid-19 we are behind schedule, however, we have asked David to provide additional staff so hopefully we will be able to make up for lost time.
The plan for the next 3-4 weeks is to concentrate the majority of works to C-Loop as well as finishing grades on all constructed tees.