During week 12 one of the main tasks was to turf the remaining tees, A1, A9, A5, A6, with B1 and a small amount on B2 to be finished.

Please see the video section for a timelapse video of the turfing of A6 tee.

In the week ahead concrete and Durabunker will be installed on B8 and B9 and possibly B2.

Shaping will continue on B3, B4, B6 and B5.